Question: table [ [ Time ( hours ) , Load ( MW ) ] , [ 6 AM - 8 AM , 1 . 2

\table[[Time (hours),Load(MW)],[6 AM -8 AM,1.2],[8 AM -9 AM,2.0],[9 AM -12 Noon,3.0],[12 Noon -2 PM,1.50],[2 PM -6 PM,2.50],[6 PM -8 PM,1.80],[8 PM -9 PM,2.0],[9 PM -11 PM,1.0],[11 PM -5 AM,0.50],[5 AM -6 AM,0.80]]
(a) Plot the load curve and find out the load factor.
(b) Determine the proper number and size of generating units to supply this load.
(c) Find the reserve capacity of the plant and plant factor.
(d) Find out the operating schedule of the generating units selected.