Question: table [ [ , Time ( weeks ) , Immediate,,Time ( weeks ) , Immediate ] , [ Activity , a , m ,
tableTime weeksImmediate,,Time weeksImmediateActivityPredecessorsActivity,PredecessorsAGC EBAHFCAFDAJD G HEBKI, JFC E
a The expected estimated time for activity is weeks Round your response to two decimal places.
b The variance for activity is weeks. Round your response to two decimal places.
c Based on the calculation of the estimated times, the critical path is AB EF
d The estimated time for the critical path is weeks Round your response to two decimal places
e The activity variance along the critical path is weeks. Round your response to two decimal places.
Using the standard normai table, the probability that Hopkins Hospitality will finish the project in weeks or less is
Enter as a probability and round your respons
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock