Question: Take a look at the following data: Job Processing Time (days) 8 10 Due Date (days) 20 B 18 C 5 25 D 11 17

Take a look at the following data: Job Processing Time (days) 8 10 Due Date (days) 20 B 18 C 5 25 D 11 17 E 9 35 If you use the FCFS, DD and SPT priority rules, what are the average tardiness and average flow time? Fill in the numbers in the table below: Priority Rule Average Tardiness Average Flowtime FCFS DD SPT Which rule performs the best