Question: Takt Time C . Flow B . Value Stream Mapping A . Theory of Constraints A . It is primarily focused on activity durations for
Takt Time
C
Flow
B
Value Stream Mapping
A
Theory of Constraints
A
It is primarily focused on activity durations for effective project implementation. The primary scheduling objective is to reduce project activities' uncertainty and duration to make scheduling reliable.
B
Generates a process flow diagram of activities and other project information. It is a wellaccepted method of displaying the process steps and workflow and then providing a system to analyse these practices in creating an effective improvement plan
C
Inputs craftspeople material, equipment, information are furnished at the same rate or faster so that process and output production is not delayed. There are two types of process and operation. The optimal process is reached when value is added constantly in preparation and installation with no waste
D
Customer schedule expectation or contract deadline. This typically is coupled with a contingency of time so the customer is not disappointed or contract damage clauses are invoked.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock