Question: Takt time = Daily operating time ? ? Required quantity per day. If our daily sales rate is 1 5 2 0 units and we
Takt time Daily operating time Required quantity per day. If our daily sales rate is units and we have two shifts of hours minus minutes each for breaks what is our takt time?
minutes or secolans or units per minute
minutes or seconds or units per minute
minutes or seconds or units per minute
minutes or seconds or units per minute
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock