Question: Talia is working on a Task A which is on a project's critical path. She has worked on Task A for other projects in the
Talia is working on a Task A which is on a project's critical path. She has worked on Task A for other projects in the past and this is the fifth time she is working on Task A. AssumeTalia is (and always has been) very highly motivated (engagement/productivity factor = 100%) and that she took 12 days on her first Task A attempt and 10 days on her second Task A attempt. How long will she take this time around (on her fifth attempt)?