Question: Tara Smith is managing a condominium project with a stipulated price contract of $15,000,000. The contract duration for the project is 12 months. They are
Tara Smith is managing a condominium project with a stipulated price contract of $15,000,000. The contract duration for the project is 12 months. They are preparing a job cost report at Month 4. The progress data to date indicates that they have completed work valued at 30% of the contract at the actual cost of $5,500,000. Assuming that the work was scheduled uniformly throughout the duration of the project, what would be the percent cost overrun at completion of the project? Use the Earned Value Method."
Step by Step Solution
3.40 Rating (144 Votes )
There are 3 Steps involved in it
Given Contract Price CP 15000000 Contract Duration 12 months Current Month t 4 Percent Complete PCI ... View full answer
Get step-by-step solutions from verified subject matter experts
