Question: Task 1: 30 Task 2: 30 10ms Task3: 20 5ms Question 1: With Completely Fair Scheduler, suppose sched_latency=6, min_granularity=2. What is the average turnaround time?

 Task 1: 30 Task 2: 30 10ms Task3: 20 5ms Question

Task 1: 30 Task 2: 30 10ms Task3: 20 5ms Question 1: With Completely Fair Scheduler, suppose sched_latency=6, min_granularity=2. What is the average turnaround time? Question2: With Multi-level Feedback Queue, suppose there are four queues and time_slice=5ms for all queues. What is the average turnaround time