Question: Task 1 - cashflow: Prepare a cash flow forecast in a tabular form with reference to the following information: Contract Sum: $$6,587,400 (excl GST) Contract
Task 1 - cashflow:
Prepare
a cash flow forecast in a tabular form with reference to the following information:
Contract Sum: $$6,587,400 (excl GST)
Contract Period -12 months
Defects Liability Period - 12 months
Retention: 10% from each interim payment (5% maximum of the contract sum)
Half released at the practical completion
Other half released at the end of defects liability period
An advanced payment of 10% of contract sum is paid on two installments as follows:
5% at the beginning of the project 5% at the end of third month
Advance payment is recovered (deducted) as follows: 6th month: $213, 210
8th month: $221, 650 10th month: $ 223, 880
provide the 10 steps
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
