Question: Task 2 [14] Given the WBS below for the automation project Task Duration Preceding A 3 - B 3 - C 14 A D 12
Task 2 [14]
Given the WBS below for the automation project
| Task | Duration | Preceding |
| A | 3 | - |
| B | 3 | - |
| C | 14 | A |
| D | 12 | B,C |
| E | 21 | C |
| F | 20 | D |
| G | 16 | E,F |
2.1. Draw the network diagram. (2)
2.2. Determine the Early start, Late start, Early finish, Late finish and Slack (7)
2.3. Draw the Gantt chart. (5)