Question: Task 2 . Total Cost Compute the mean and variance of the total cost using the two rules for the sum of independent random variables.
Task Total Cost
Compute the mean and variance of the total cost using the two rules for the sum of independent random variables.
Task Cost Risk Assessment using PERT
Using the PERT results from Task answer the questions below.
Q Determine the most likely cost of the total cost.
Answer:
Q The probability of completing the project within $ would be most likely
A About
B About
C About
D About
Q Determine the total cost when the required probability of completing the project within the budget is
Answer:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
