Question: Task 3 Review the beam from Task 1 . An agreement with the construction team has been reached to delay applying the permanent load and
Task
Review the beam from Task An agreement with the construction team has been reached to delay applying the permanent load and of the variable load to reduce excessive deflection and meet SLS criteria. Identify the earliest possible time to apply these loads.