Question: Task 5 of ABC project has a 3 0 - day timeline and $ 1 , 0 0 0 budget. After 1 5 days, the

Task 5 of ABC project has a 30-day timeline and $1,000 budget. After 15 days, the project manager finds that 50% of the project is complete and the actual cost is $450 and planned value is $475. What is cost variance percent?
5
95
90
10