Question: Task Description Dur * Pred 1 Obtain HW 3 0 - 2 Coding 6 0 - 3 Write test plans 1 0 0 - 4

Task Description Dur* Pred
1 Obtain HW 30-
2 Coding 60-
3 Write test plans 100-
4 Write training manuals 100-
5 Install and test HW 351
6 Integration testing 302,5
7 System testing 703,6
8 Install SW (user site)107
9 User training 104,8
10 Acceptance testing 109
*Duration (Dur) is in days
Implementation phase of IT project has ten tasks, as shown above.
Complete the table below:
1) TE is the earliest completion time.
Forward pass: TE(activity)= latest TE(predecessor)+ Duration(activity)
2) TL is the latest completion time.
Backwards pass: TL(predecessor)= TL(activity) Duration(activity)
3) Slack = TL TE
4) Critical Path goes from start to finish with activities of zero slack
Task Description Dur Pred TE TL Slack
1 Obtain HW 30-30
2 Coding 60-60
3 Write test plans 100-
4 Write training manuals 100-
5 Install and test HW 351
6 Integration testing 302,5
7 System testing 703,6
8 Install SW (user site)107
9 User training 104,8
10 Acceptance testing 109
What is the Critical Path? ________________________________

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!