Question: Task Description Duration (days) Predecessor 1 Site levelling 7d None 2 Lay foundation 14d 1 3 Erect walls 42d 2 4 Company offices 14d 3
| Task | Description | Duration (days) | Predecessor |
| 1 | Site levelling | 7d | None |
| 2 | Lay foundation | 14d | 1 |
| 3 | Erect walls | 42d | 2 |
| 4 | Company offices | 14d | 3 |
| 5 | Laying Drainage | 14d | 2 |
| 6 | Build production rooms | 21d | 5 |
| 7 | Build cafeteria | 7d | 5 |
| 8 | Fit electrical & plumbing Services | 14d | 4,6,7 |
| 9 | Machines installation | 7d | 8 |
| 10 | Erecting Perimeter wall | 21d | 1 |
| 11 | New site fully operational | 0d | 9,10 |
Use the above to prepare a network diagram and Gantt Charts. Show the critical path.( Use ms-project package )