Question: Task Description Duration Dependency A Visit the client for the requirement 3 - B Identify the User requirement 10 A C Developed the SRS 5
| Task | Description | Duration | Dependency |
| A | Visit the client for the requirement | 3 | - |
| B | Identify the User requirement | 10 | A |
| C | Developed the SRS | 5 | B |
| D | Design the interface | 4 | B |
| E | Set-up Server | 7 | C |
| F | Test the site | 6 | D, E |
| G | Develop an inspection team | 5 | D, F |
| H | Train User | 3 | E, G |
| I | Review the client feedback | 2 | H, G |
- Create the activity network diagram for the following tasks
- Identify all the possible path, identify the critical path and what is the significance of critical path data updates?
- What does task Dependency tell us in the project? Explain its type with example?