Question: Task Description Immediate Predecessors Optimistic Time ( O ) Most Likely Time ( M ) Pessimistic Time ( P ) A Shut down the warehouse

Task Description Immediate Predecessors Optimistic Time (O) Most Likely Time (M) Pessimistic Time (P)
A Shut down the warehouse system and remove old servers from the server room none 1 hour 2 hours 3 hours
B Install new computer servers in the server room A 1 hour 2 hours 9 hours
C Reconfigure warehouse terminals none 2 hours 4 hours 6 hours
D Reboot the warehouse system and run diagnostics B and C 2 hours 6 hours 16 hours