Question: Task Description Immediate Predecessors Optimistic Time ( O ) Most Likely Time ( M ) Pessimistic Time ( P ) A Shut down the warehouse
Task Description Immediate Predecessors Optimistic Time O Most Likely Time M Pessimistic Time P
A Shut down the warehouse system and remove old servers from the server room none hour hours hours
B Install new computer servers in the server room A hour hours hours
C Reconfigure warehouse terminals none hours hours hours
D Reboot the warehouse system and run diagnostics B and C hours hours hours
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock