Question: Task Due date Status Create customer list March 30 complete Write reports March 23 complete Meeting prep March 25 complete Today is March 20 .
| Task | Due date | Status |
| Create customer list | March 30 | complete |
| Write reports | March 23 | complete |
| Meeting prep | March 25 | complete |
Today is March 20 . Which task should be the first priority? a. Create customer list b. Write reports c. Meeting prep