Question: Task Duration (minutes) Immediate Predecessor A 0.6 - B 0.5 A C 0.3 B D 0.4 - E 1.8 D F 0.8 C G 1.2

Task

Duration (minutes)

Immediate Predecessor

A

0.6

-

B

0.5

A

C

0.3

B

D

0.4

-

E

1.8

D

F

0.8

C

G

1.2

E, F

  1. Use a table to assign tasks to workstations on the basis of most following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
  1. Compute the percentage of idle time for the assignment in part d.

Cycle time = 2 minutes per cycle