Question: Task Duration Predecessor Budget Status Actual Cost % Complete K 8 Start $6000 Completed $5000 100% D 6 K (SS+2) $3000 Completed $2000 100% B

Task Duration Predecessor Budget Status Actual Cost % Complete K 8 Start $6000 Completed $5000 100% D 6 K (SS+2) $3000 Completed $2000 100% B 10 K,D(FS+2) $4000 Completed $2500 100% L 8 K,B (FF+2) $4000 20% complete $1500 20% E 4 L $2000 60% complete $1000 60% F 4 E (SS+4) $2000 80% complete $2000 80% G 10 F,L(SF+10) $7000 Not started $0 0% End G