Question: Task Immediate Predecessor Task Length (Days) A 2 B A 3 C B 1 D B 4 E C,D 2 What is the critical path?

Task

Immediate Predecessor

Task Length (Days)

A

2

B

A

3

C

B

1

D

B

4

E

C,D

2

What is the critical path?

A-B-D-E

A-C-E-F

B-D-E-F

A-F-G-H

Calculate the expected completion time.

7 days

11 days

19 days

20 days

What is the slack for task C?

1 day

3 days

5 days

7 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock