Question: Task Immediate Predecessor Task Time (minutes) a - 0.9 b a 0.4 c b 0.6 d c 0.2 e c 0.3 f d, e 0.4
| Task | Immediate Predecessor | Task Time (minutes) |
| a | - | 0.9 |
| b | a | 0.4 |
| c | b | 0.6 |
| d | c | 0.2 |
| e | c | 0.3 |
| f | d, e | 0.4 |
| g | f | 0.7 |
| h | g | 1.1 |
| t = 4.6 | ||
- Given the data, assign tasks to workstations using the longest task-time heuristic. Fill-up the table below.
|
Station | Time Remaining |
Eligible | Assign (Task Time) |
Idle Time |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Compute for the Percentage Idle Time, Efficiency of the line
c) Draw the Balanced Line.