Question: Task must follow task listed below Task Assembly Time (minutes) A 7 B 7 14 D 5 E 8 F 7 G 14 H 6

 Task must follow task listed below Task Assembly Time (minutes) A

Task must follow task listed below Task Assembly Time (minutes) A 7 B 7 14 D 5 E 8 F 7 G 14 H 6 1 5 J 10 K 4 L 13 Total Time 100 A A B B E, F, G D D 1 H, K,J Toyota wants to develop a precedence diagram for an engine component that requires a total assembly time of 100 minutes. Furthermore, the production schedule requires that 34 units of the engine component to be completed as output from the assembly line each day. Toyota determines that there are 510 productive minutes of work available per day. 1- Draw the precedence diagram 2- Calculate the cycle time 3. Find (Calculate) minimum number of workstations 4- Balance the line by assigning specific assembly tasks to each workstation. Task must follow task listed below Task Assembly Time (minutes) A 7 B 7 14 D 5 E 8 F 7 G 14 H 6 1 5 J 10 K 4 L 13 Total Time 100 A A B B E, F, G D D 1 H, K,J Toyota wants to develop a precedence diagram for an engine component that requires a total assembly time of 100 minutes. Furthermore, the production schedule requires that 34 units of the engine component to be completed as output from the assembly line each day. Toyota determines that there are 510 productive minutes of work available per day. 1- Draw the precedence diagram 2- Calculate the cycle time 3. Find (Calculate) minimum number of workstations 4- Balance the line by assigning specific assembly tasks to each workstation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!