Question: Task Name: Project Preparation Sub Task 1: Develop Project Plan Duration: 1 month (March 1st, 2022 to April 1st, 2022) Task Name: Site Preparation Sub

Task Name: Project Preparation Sub Task 1: Develop Project Plan Duration: 1 month (March 1st, 2022 to April 1st, 2022)

Task Name: Site Preparation Sub Task 1: Conduct site survey Duration: 3 weeks (April 4th, 2022 to April 24th, 2022) Sub Task 2: Obtain necessary permits Duration: 2 weeks (April 25th, 2022 to May 8th, 2022) Sub Task 3: Demolition of existing structures Duration: 3 weeks (May 9th, 2022 to May 29th, 2022)

Task Name: Foundation Work Sub Task 1: Excavation Duration: 4 weeks (June 1st, 2022 to June 26th, 2022) Sub Task 2: Concrete pouring and curing Duration: 6 weeks (June 27th, 2022 to August 7th, 2022)

Task Name: Framing and Rough-ins Sub Task 1: Framing Duration: 6 weeks (August 8th, 2022 to September 18th, 2022) Sub Task 2: Electrical, plumbing and HVAC rough-ins Duration: 4 weeks (September 19th, 2022 to October 16th, 2022)

Task Name: Finishing Work Sub Task 1: Drywall installation Duration: 4 weeks (October 17th, 2022 to November 13th, 2022) Sub Task 2: Painting Duration: 2 weeks (November 14th, 2022 to November 27th, 2022) Sub Task 3: Flooring Duration: 2 weeks (November 28th, 2022 to December 11th, 2022) Sub Task 4: Cabinetry and countertops Duration: 2 weeks (December 12th, 2022 to December 25th, 2022)

Task Name: Final Inspection and Punch List Sub Task 1: Final inspection Duration: 1 week (December 26th, 2022 to January 2nd, 2023) Sub Task 2: Punch list completion Duration: 2 weeks (January 3rd, 2023 to January 16th, 2023)

Task Name: Closeout Sub Task 1: Obtain certificate of occupancy Duration: 1 week (January 17th, 2023 to January 23rd, 2023) Sub Task 2: Substantial completion Duration: 1 week (January 24th, 2023 to January 30th, 2023)

detailed project activity list that is consistent with scope, major deliverables, WBS and WBS Dictionary. Use any Software (Word, Excel, MS Project, Teamgantt etc.) to develop the project Gantt chart covering all activities that have been identified. The Gantt chart must clearly identify and show:

  • WBS codes,
  • Project timeline,
  • Milestones to complete the project,
  • Activities predecessors and successors,
  • Activities start and finish dates,
  • Project critical path
  • Allocated resources

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!