Question: Task Performance Time (seconds) Immediate Predecessors A 22 - B 28 A C 15 A D 15 A E 12 B, C F 27 D,

Task Performance Time (seconds)
Immediate Predecessors
A 22 -
B 28 A
C 15 A
D 15 A
E 12 B, C
F 27 D, E
Task Performance Time (seconds) Immediate
Given the demand, the cycle time for the production of the new train set =____ seconds. (Round your answer to one decimal place)
The Action Toy Compary has decided to manufacturo a new train set, the production of which is broken into six stopa. The domand for the train is 4,600 units per 40 hour workwook Performance Time (seconds) Predecessors Task B 22 28 15 15 12 27