Question: Task Performance Time (seconds) Immediate Predecessors A 22 - B 28 A C 15 A D 15 A E 12 B, C F 27 D,
Task Performance Time (seconds)
Immediate Predecessors
A 22 -
B 28 A
C 15 A
D 15 A
E 12 B, C
F 27 D, E

Given the demand, the cycle time for the production of the new train set =____ seconds. (Round your answer to one decimal place)