Question: Task Precedence Relation a m b A None 8 10 18 Problem 13 B A 5 7 9 C B 14 18 22 D B

Task Precedence Relation a m b A None 8 10 18

Task Precedence Relation a m b A None 8 10 18 Problem 13 B A 5 7 9 C B 14 18 22 D B 2 3 4 E C 7 9 11 F D 7 9 11 G E 7 9 11 H E 4 6 8 I E 4 5 6 J I 12 15 18 K F G 2 3 4 L KH 8 10 12 M J.L 20 28 36 N J.L 8 10 18 o N 6 8 10 P M,O 15 19 23 Q 16 20 36 What is the chance of completing the project by 130 and 140 time units? 14