Question: Task Preceding Task to tm tp te A None 1 12 18 11.2 B A 10 13 15 12.8 C B 4 5 9 5.5
Task Preceding Task to tm tp te A None 1 12 18 11.2 B A 10 13 15 12.8 C B 4 5 9 5.5 D B 9 10 15 10.7 E C, D 7 8 12 8.5 Find the critical path for the following project (task times are in weeks).
Find the critical path for the following project (task times are in weeks)