Question: TASK PRECEDING TASKS PERFORMANCE TIME ( SECONDS ) TASK PRECEDING TASKS PERFORMANCE TIME ( SECONDS ) a 2 7 g d 1 4 b 2

TASK PRECEDING TASKS PERFORMANCE TIME (SECONDS) TASK PRECEDING TASKS PERFORMANCE TIME (SECONDS)
a 27 g d 14
b 28 h e 34
c 43 i f 8
d a 10 j g 6
e b 33 k h,i 38
f c 13 l j,k 13
b. What is the workstation cycle time required to produce 600 units per day?