Question: TASK PRECEDING TASKS TIME ( SECONDS ) A 1 9 B A 1 6 C A 1 0 D B 1 5 E B 1
TASK PRECEDING TASKS TIME SECONDS
A
B A
C A
D B
E B
F C
G C
H D
I E
J F G
K H I
L J K
What is the required workstation cycle time to meet the desired output rate?