Question: Task Relationships. The task interface diagram graphically identifies the relationships between tasks using any one of four specific relationships: Finish-start: Task A must be completed

Task Relationships. The task interface diagram graphically identifies the relationships between tasks using any one of four specific relationships: Finish-start: Task A must be completed before task B can begin (this is the most common link) Finish-finish: Task B must be completed before task C can be completed