Question: Task Successor Duration A B,C 8 B D 12 C E,F 16 D G,H 14 E H 13 F I 19 G I 8 H
Task | Successor | Duration |
A | B,C | 8 |
B | D | 12 |
C | E,F | 16 |
D | G,H | 14 |
E | H | 13 |
F | I | 19 |
G | I | 8 |
H | I | 14 |
I | NONE | 12 |
Find the Forward Pass, Backward Pass and Float for each task and show them on your network diagram
Identify the Critical path and explain why it is the critical path. Show any non critical paths
In the event that the duration of Task C is changed to 14 days, identify if the critical path changes and also identify any float changes in each task