Question: Task Successor s Duration (weeks) Early Start Time Late Start Time Free Slack Total Slack Trimmed Duration Trimmed Early Start Trimmed Late Start Trimmed Free

Task Successor s Duration (weeks) Early Start Time Late Start Time Free Slack Total Slack Trimmed Duration Trimmed Early Start Trimmed Late Start Trimmed Free Slack Trimmed Total Slack A B,C 3 0 0 B D 4 3 3 C E,F 2 3 5 D G 5 E G 4 F H 6 G I 3 H I 2 I J 2 J none 4 Finish What is/are the critical paths? Interpret the free slack and total slack values for activity C. What do they indicate? Trim two weeks from the project by shortening task G Recalculate the free and total slack. What is/are the critical paths