Question: TASK TASK TIME ( SECONDS ) IMMEDIATE PREDECESSOR A 3 5 B 4 0 A C 3 5 A D 4 0 B E 1

TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR
A 35
B 40 A
C 35 A
D 40 B
E 15 C
F 75 C
G 45 E-F
H 30 D-G Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion