Question: Task Time (days) Predecessor A 10 ----- B 17 A C 22 A D 30 B,C E 27 C F 20 C G 8 D
| Task | Time (days) | Predecessor |
| A | 10 | ----- |
| B | 17 | A |
| C | 22 | A |
| D | 30 | B,C |
| E | 27 | C |
| F | 20 | C |
| G | 8 | D |
| H | 15 | E |
| I | 12 | G,H,F |
- Critical path
- Project duration
- ES, EF, LS, LF, and S for each task