Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Time (in hours) Immediate Predecessor(s)
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
| Activity | Time (in hours) | Immediate Predecessor(s) |
| A | 7.0 | |
| B | 7.2 | |
| C | 6.0 | A |
| D | 8.0 | B, C |
| E | 4.8 | B, C |
| F | 8.1 | D |
| G | 4.0 | E, F |
This exercise contains only part a.
a) The correct precedence diagram for the project is shown in
Figure 3
Figure 1
Figure 2
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
| Activity | Time (in hours) | Immediate Predecessor(s) |
| A | 7.0 | |
| B | 7.2 | |
| C | 6.0 | A |
| D | 8.0 | B, C |
| E | 4.8 | B, C |
| F | 8.1 | D |
| G | 4.0 | E, F |
This exercise contains only part a.
a) What is the correct precedence diagram for the project
..
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts