Question: Task time estimates for the modification of an assembly line at Jim Goodales Carbondale, Illinois, factory are as follows: ACTIVITY TIME (IN HOURS) IMMEDIATE PREDECESSORS
Task time estimates for the modification of an assembly line at Jim Goodales Carbondale, Illinois, factory are as follows: ACTIVITY TIME (IN HOURS) IMMEDIATE PREDECESSORS A 6.0 B 7.2 C 5.0 A D 6.0 B, C E 4.5 B, C F 7.7 D G 4 E, F (a) Draw the project network using AON. (b) Identify the critical path. (c) What is the expected project length? (d) Draw a Gantt chart for the project