Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale. Illinois, factory are as follows: ACTIVITY TIME ( IN HOURS )

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale. Illinois, factory are as follows:
ACTIVITY TIME (IN HOURS) IMMEDIATE PREDECESSORS
A 6.0----
B 7.2----
C 5.0 A
D 6.0 B, C
E 4.5 B, C
F 7.7 D
G 4.0 E, F
a. Identify the critical path
b. What is the expected project completion time?
a. Critical path = A-C-D-F-G
b. Completion time =28.7
a. Critical path = A-C-D-F-G
b. Completion time =28.0
a. Critical path = A-C-D-F-E
b. Completion time =28.7
a. Critical path = A-C-D-F-G
b. Completion time =26.7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!