Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: table [ [ Actlvity ,

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
\table[[Actlvity,\table[[Time],[(in hours)]],Immediate Predecessor(s)],[A,7.0,-],[B,6.7,-],[C,5.0,A],[D,8.0,B, C],[E,4.8,B, C],[F,7.7,D],[G,6.0,E, F]]
This exercise contains only part a.
a) The correct precedence diagram for the project is shown in Figure 2.