Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Task time estimates for the modification
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:



Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Immediate Predecessor(s) Time (in hours) 7.0 6.7 6.0 A onmou) 6.0 4.5 B, C B, C D E, F 8.1 6.0 This exercise contains only part a. a) The correct precedence diagram for the project is shown in Figure 1 Figure 2 o os Figure 3