Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Time (in hours) Immediate Predecessor(s)
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:
| Activity | Time (in hours) | Immediate Predecessor(s) |
| A | 7 | - |
| B | 6.5 | - |
| C | 4 | A |
| D | 5 | B, C |
| E | 4 | B, C |
| F | 6.5 | D |
| G | 4 | E, F |
This exercise contains only parts d, b, and c.
Part 2
d) Using the line drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times.
Carefully follow the instructions above, and only draw the required objects.
Part 3
b) The critical path activities for the leadership training program development project are
A - C - D - F - G
.
Part 4
c) The expected project completion time for the leadership training program development project =
26.526.5
hours (round your response to one decimal
place).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts