Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

Activity Time (in hours) Immediate Predecessor(s)
A 7 -
B 6.5 -
C 4 A
D 5 B, C
E 4 B, C
F 6.5 D
G 4 E, F

This exercise contains only parts d, b, and c.

Part 2

d) Using the line drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times.

Carefully follow the instructions above, and only draw the required objects.

Part 3

b) The critical path activities for the leadership training program development project are

A - C - D - F - G

.

Part 4

c) The expected project completion time for the leadership training program development project =

26.526.5

hours (round your response to one decimal

place).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!