Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Time Immediate Predecessor(s) (in hours)
| Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: | ||
| Activity | Time | Immediate Predecessor(s) |
| (in hours) | ||
| A | 6 | - |
| B | 7 | - |
| C | 5 | A |
| D | 6 | B, C |
| E | 4.5 | B, C |
| F | 8 | D |
| G | 4 | E, F |
| This exercise contains only parts d, b, and c. | ||
| Part 2 | ||
| d) Using the line drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times. | ||
| Carefully follow the instructions above, and only draw the required objects. |