Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Ilinois, factory are as follows: Activity A B C D
Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Ilinois, factory are as follows: Activity A B C D Time (in hours) Immediate Predecessor(s) 5.0 7.2 4.0 7.0 4.8 8.1 4.0 A B,C B,C D E.F E F G This exercise contains only part a a) The correct precedence diagram for the project is shown in t Figure 1 Figure 2 Figure 3
Step by Step Solution
3.38 Rating (154 Votes )
There are 3 Steps involved in it
The correct precedence diagram for the project based on the given task tim... View full answer
Get step-by-step solutions from verified subject matter experts
