The optimistic, most likely and pessimistic times for the tasks comprising a project are shown below. Use the data to compute the expected completion time and variance for each task.

LOADING...

Click the icon to view the table of the optimistic, most likely, and pessimistic times.

Part 2

Find the expected completion time and variance for each task and fill in the table below (enter your responses rounded to two decimal places).

Task

to

tm

tp

te

s2t

A

10

15

19

enter your response here

enter your response here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!