Question: Task/Activity Task/Activity Name Duration(days) Predecessor A Store sign banner 7 13 B Feasibility study 6 NON C select qualified employees 20 2 D Quality training
| Task/Activity | Task/Activity Name | Duration(days) | Predecessor |
| A | Store sign banner | 7 | 13 |
| B | Feasibility study | 6 | NON |
| C | select qualified employees | 20 | 2 |
| D | Quality training | 10 | 3 |
| E | Advertising | 8 | 14 |
| F | Secure spares suppliers | 5 | 9 |
| G | Secure cars suppliers | 6 | 6 |
| H | Finding a suitable place | 9 | 2 |
| I | Import cars | 40 | 7 |
| J | Decoration kits | 6 | 9 |
| K | Market testing | 10 | 4 |
| L | Complete the requirements of the municipality | 16 | 8 |
| M | Register trademark | 4 | 12 |
| N | Design of publication | 5 | 10 |
| O | Prepare car shop launch | 3 | 4,10.11,8,12,13,9 |
question:::::
A. Draw Labeled Network Diagram and high light critical path
- Calculate total duration.
- Make a list of all Critical Activities
- Make a list of all Non-Critical Activities
- Find Total Float/ Slack for Each Activity
Step by Step Solution
There are 3 Steps involved in it