Question: Tasks 1 , 2 , and 3 are selected in the image below. What will result when the Insert Summary Task menu option is selected?
Tasks and are selected in the image below. What will result when the Insert Summary Task menu option is selected?
a
A new summary task and a subtask are created and replace the selected rows.
b
A new summary task is created above the selected tasks and the selected tasks become subtasks beneath the summary task.
c
An error occurs as you cannot have tasks selected when you insert a new summary task.
d
A new task is inserted above and at the same level as the selected tasks.