A simple project listing of five activities, their predecessors, and their respective time estimates are presented below:
\table[[Activity,Immediate Predecessor,Time in Days],[A,None,2],[B,A,2],[C,A,1],[D,B and C,3],[E,D,1]]
Using the CPM, which activities have slack in this project? (Select all that apply.)