Question: TB MC Qu . 0 2 - 4 5 If all you knew about a . . . If all you knew about a production
TB MC Qu If all you knew about a
If all you knew about a production system was that total daily output was units and the total labor necessary to produce the units was hours, and the total materials used were units, what kind of productivity measures could you use to compute productivity?
Multiple Choice
Partial measure
Multifactor measure
Total measure
Partial measure and Multifactor measure