Summerlin Company budgeted 4,800 pounds of material costing $7.00 per pound to produce 2,100 units. The company actually used 5,300 pounds that cost $7.10 per pound to produce 2,100 units. What is the direct materials quantity variance?
Multiple Choice
$3,500 unfavorable.
$480 unfavorable.
$530 unfavorable.
$3,550 unfavorable.
$4,030 unfavorable.