TB MC Qu.16-80 The owner/operator of the local franchise of... The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?