Question: TB MC Qu . 1 9 - 0 9 All activities must be All activities must be before a new activity can be started in
TB MC Qu All activities must be
All activities must be before a new activity can be started in a project.
Multiple Choice
predecessor, started
successor, completed
predecessor, completed
successor, started